Heathrow says third runway could open in 2039 as 2035 target slips
The airport aims to secure planning permission by 2029 and says opening a third runway could take up to a decade after that. Ministers say the 2035 target was always ambitious.
Heathrow says its proposed third runway could open as late as 2039, four years after the government’s 2035 target, because it expects construction and opening to take up to a decade after planning permission. The airport aims to secure that permission by 2029, making the opening date a projection rather than an approved timetable.
The airport told Reuters that opening within a decade of permission has always been its core scenario. It described the 2035 target as ambitious and said meeting it would have required significant changes to regulation and policy. Heathrow also told the BBC it would work with ministers, airlines and other stakeholders to advance the application.
The decisions still ahead
The Department for Transport’s April programme letter set out an operational runway by 2035 and a development consent order by 2029 as objectives. It assigns the promoter responsibility for planning, financing and building the expansion, subject to the outcome of its application. Heathrow’s latest account therefore highlights a gap between the government’s operational goal and the airport’s stated delivery scenario.
A draft government policy statement sets out how any Heathrow expansion proposal would be assessed, including its effects on air quality, climate, communities and noise. The Department for Transport says the draft does not grant permission to build. It must be finalised and considered by Parliament, and a promoter would still have to submit a planning application through the statutory process.
The department told the BBC on 26 September that there was no live planning application for a third runway. It said the timeline had always been ambitious and that it would continue working with Heathrow and other stakeholders on the framework needed to consider an application. Whether the runway opens in 2035, 2039 or at another time depends on decisions and work that have yet to take place.
Read in depth: Business
ECB warns AI valuations and sovereign debt could threaten financial stability
The European Central Bank says ambitious AI earnings expectations and sovereign debt pressures could expose the euro area to shocks, though banks have strong buffers.
Nvidia raises revenue growth forecast as Colette Kress presents first earnings
The chipmaker beat quarterly revenue expectations and raised its longer-term outlook in its first earnings presentation since Jensen Huang resigned as CEO.
What this story rests on
4 sources from 3 organisations: 1 news agency, 2 official sources, 1 broadcaster.
- 1Heathrow Airport warns third runway could be delayed by four yearsBBC News · bbc.co.ukBroadcaster
- 2UK's Heathrow airport says planned third runway may be delayed until 2039Reuters (republished by MarketScreener) · marketscreener.comNews agency
- 3About the draft Heathrow Expansion National Policy Statement (HENPS)Department for Transport · gov.ukOfficial source
- 4Heathrow Expansion programme SRO appointment letterDepartment for Transport · gov.ukOfficial source
AI-assisted article checked against the listed sources. NewsJaws did not conduct interviews or attend the reported events.
Researched and drafted with AI tools from these sources, then checked against them paragraph by paragraph before publication. How we work · Everyone we cite · Report an error