North Devon residents oppose proposed 1.5GW AI data campus as planning decision awaits
Xlinks proposes a data centre and battery facility near Great Torrington. Residents have raised concerns about the landscape, water use and safety, while the council says formal applications have yet to arrive.
Residents in north Devon are organising against a proposed large AI data campus and battery facility near Great Torrington, as the project awaits formal planning applications. The dispute matters because the scheme would occupy countryside within a Unesco-designated biosphere reserve, while its effects on the area have yet to be tested through the planning process.
Xlinks proposes separate developments between Great Torrington, Huntshaw and Weare Giffard: a data centre with up to 1.5 gigawatts of capacity and an on-site battery energy storage facility rated at 1.8 gigawatts. Those figures describe the company's plans, not operating facilities. Data Center Dynamics reported the project announcement in June.
What residents and Xlinks say
The Guardian reported on 27 September that campaigners object to the proposed location and have raised concerns about water use, changes to the landscape and battery safety. These are concerns about potential effects, not findings that those effects have occurred. Protesters gathered outside a Torridge District Council meeting this week, according to the newspaper.
Xlinks says the campus would involve £12.2 billion to £13.8 billion in capital investment and support 600 to 1,200 permanent operational jobs. These are company forecasts. Xlinks told the Guardian it plans to recirculate water and is carrying out environmental surveys; it said any required mitigation would be built into the design and secured through planning conditions.
Planning status
Torridge District Council says it has received no formal planning applications for the proposals. According to its published statement, Xlinks sought pre-planning advice for the data campus in April 2025 and for the battery facility in October 2025. Such discussions do not amount to planning approval.
The council says a public consultation planned for July 2026 was postponed until later in the year, with new dates still unpublished when it issued its statement. It told the Guardian that applications, once received, would be validated and published on its planning portal. The timing of a formal decision therefore remains unknown.
Read in depth: Business
ECB warns AI valuations and sovereign debt could threaten financial stability
The European Central Bank says ambitious AI earnings expectations and sovereign debt pressures could expose the euro area to shocks, though banks have strong buffers.
Nvidia raises revenue growth forecast as Colette Kress presents first earnings
The chipmaker beat quarterly revenue expectations and raised its longer-term outlook in its first earnings presentation since Jensen Huang resigned as CEO.
What this story rests on
4 sources from 4 organisations: 1 official source, 1 newspaper or magazine, 2 news outlets.
- 1‘People are standing up and fighting back’: the north Devon revolt against a vast AI datacentreThe Guardian · theguardian.comNewspaper or magazine
- 2Statement from Torridge District Council regarding the proposed Devon data centreTorridge District Council · torridge.gov.ukOfficial source
- 3Devon data campusXlinks · xlinks.coNews outlet
- 41.5GW data center campus proposed in Devon, UKData Center Dynamics · datacenterdynamics.comNews outlet
AI-assisted article checked against the listed sources. NewsJaws did not conduct interviews or attend the reported events.
Researched and drafted with AI tools from these sources, then checked against them paragraph by paragraph before publication. How we work · Everyone we cite · Report an error